Machine
Shop 2 |
Lathe Operations - Project - Tap Handle 2
| Part #
Part Description: Casting Setup Quantity Req.: 1 |
Name _________________________
Date: ________________ |
PLEASE HAVE YOUR INSTRUCTOR INITIAL AND DATE THE GREY BOXES (*) AFTER THE REQUIRED OPERATIONS.
| Step# | Location | Description | Initials | Date |
| 10 | Instructor | Have your instructor assign a weldment or casting to setup. Have the instructor indicate the features to be machined (mock). | ||
| 20 | Student | In writing, explain the setup and the materials necessary to set the job up. Explain it as though it were for the student or co-worker who needed to set up the job the next time. | ||
| 30 | Instructor | Have your instructor check the setup explanation. | * | |
| 40 | Student | Make changes to the setup explanation as prescribed by the instructor. | ||
| 50 | Student | Make the setup. | ||
| 60 | Instructor | Have your work checked by the instructor. | * | |
| 70 | Student | Make a sketch of the setup on the last page of this project sheet. | ||
| 80 | Instructor | Have the sketch checked by the instructor. | * |
|
|